May 31, 2024 News
Check out the progress on the Neuse River Sidestream Treatment Project in Raleigh, NC! This project will remove excess nitrogen and phosphorus from the plant's dewatered filtrate flows allowing treated water to return back to the flow stream where additional treatment can occur. Highlights include:
- 130’ x 60’ concrete tank with aeration, screening, sludge collection, and mixers.
- Filtrate pump station and new service building for pumps, blowers, and electrical gear.
- New clarifier and extensive site improvements.
These upgrades will enhance wastewater treatment and accommodate the growing city of Raleigh!
ºÚÁÏ³Ô¹Ï Releases Documentary About Mission Trip to Guatemala
June 10, 2026Mission
100 Acts of Service: 51-57
June 3, 2026Mission
ºÚÁÏ³Ô¹Ï ranks No. 268 on ENR Top Contractors List
June 1, 2026News
Completion of the Ventilator Program Addition at Hattie Larlham
May 26, 2026News
100 Acts of Service: No. 50
May 20, 2026Mission
Renneker Water Treatment Plant Project Delivered
May 18, 2026News
100 Acts of Service: 37-49
May 13, 2026Mission
Occupied Renovation: What Steps Owners Need to Know to Keep People Safe and Operations Moving
May 11, 2026Insights
Groundbreaking for Bay Village Facilities Improvement Project
May 7, 2026News
100 Acts of Service: 31-36
May 6, 2026Mission
Progress at the Bedford Heights Wastewater Treatment Plant
May 5, 2026News
100 Acts of Service: 28-30
April 27, 2026Mission