April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.Â
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.Â
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Stand Down for Safety
May 18, 2023News
Teaching Preble County 4th Graders about Construction
May 17, 2023Mission
ºÚÁÏ³Ô¹Ï Construction: Solidly Built on Century of Success
May 16, 2023News
ºÚÁϳԹÏ's Indianapolis Office Wins CCS Safety Achievement Award
May 12, 2023Awards
New Kenton Ridge PK-12 facility approaching completion
May 11, 2023News
ºÚÁϳԹÏ's Kenny Bowshier Receives CCS Outstanding Craftsperson Award
May 9, 2023Awards
1ºÚÁϳԹÏ, 1Mission: Bike Build for Starfish Assignment
May 8, 2023Mission
Montgomery County SMART Project Hits Halfway Point
May 1, 2023News
Almost 100-year-old Dayton construction company shares secrets to success
April 26, 2023News
Spring 2023 Co-ops Present Their Learnings
April 20, 2023News
Leveraging Collaborative Delivery To Maintain Continuous Treatment
April 19, 2023Insights
Greene County NW Regional Water Treatment Plant Update
April 14, 2023News