April 7, 2026 News
Concrete installation has begun at Tipp City Schools’ new PK-8 School, marking a major milestone for the project! After months of planning and site preparation, construction is in full swing.
ºÚÁÏ³Ô¹Ï is serving as the construction manager for the 218,944-square-foot PK-8 school, which will serve nearly 1,800 students.
Teams recently poured 160 yards of foundational concrete in a section of the school that includes the cafeteria kitchen, mechanical room, and locker rooms. The next phase will include a foundational concrete pour in the three-story academic wing.
In addition, teams have completed:
Crews continue to make progress on underground electrical, and plumbing work and are constructing two staircases.
Stay tuned for updates as Tipp City Schools embarks on a transformative facilities construction program. ºÚÁÏ³Ô¹Ï will also manage a comprehensive renovation to Tippecanoe High School, with work taking place during the summers of 2026 and 2027.
Thank you to our design partner, Garmann Miller, and other industry partners as we work to deliver 21st-century learning environments for the district.
Ìý
Stand Down for Safety
May 18, 2023News
Teaching Preble County 4th Graders about Construction
May 17, 2023Mission
ºÚÁÏ³Ô¹Ï Construction: Solidly Built on Century of Success
May 16, 2023News
ºÚÁϳԹÏ's Indianapolis Office Wins CCS Safety Achievement Award
May 12, 2023Awards
New Kenton Ridge PK-12 facility approaching completion
May 11, 2023News
ºÚÁϳԹÏ's Kenny Bowshier Receives CCS Outstanding Craftsperson Award
May 9, 2023Awards
1ºÚÁϳԹÏ, 1Mission: Bike Build for Starfish Assignment
May 8, 2023Mission
Montgomery County SMART Project Hits Halfway Point
May 1, 2023News
Almost 100-year-old Dayton construction company shares secrets to success
April 26, 2023News
Spring 2023 Co-ops Present Their Learnings
April 20, 2023News
Leveraging Collaborative Delivery To Maintain Continuous Treatment
April 19, 2023Insights
Greene County NW Regional Water Treatment Plant Update
April 14, 2023News